Service guide

Factory Licensing Services in Thailand.

How a factory license in Thailand works: the Ror Ngor 4 under the Factory Act, official fees by machine power, the 30 day review, and the e-License route.

0 firms on Justenda.

Key facts

What does a factory license in Thailand cost?
The official fee scales with machine power: 1,000 baht with no machinery, 1,500 baht under 50 horsepower, then in steps up to 145,000 baht at the top of the published schedule. Professional fees are separate.
How long does the licence take?
The published review time is 29 days for a complete paper application and 30 days through the e-License system, counted from a complete file. Preparing the environmental documentation usually takes longer than the review.
Which form is the application?
The Ror Ngor 3, filed in two originals at the Department of Industrial Works in Bangkok or three originals at a provincial industry office, or online through e-License after registering on the i-Industry portal.
Does every factory need the licence?
No. The Factory Act reserves the Section 12 licence for the categories on its factory list. Which category an operation falls into is the first thing to confirm, because it decides the whole route.

Factory licensing, done properly.

Talk to someone who does this every week. Verified firms reply with how they would handle your case and what it costs. Free, no account needed.

What a factory license in Thailand costs

The official fee for a factory license in Thailand scales with machine power. The government service record for the Section 12 licence publishes the full schedule, from 1,000 baht for an operation with no machinery to 145,000 baht at the top of the range. Professional fees for a firm that manages the application sit on top and depend on the factory category, the site, and how much of the environmental documentation already exists.

Official factory licence fees by machine power

Selected tiers from the published fee schedule for the factory operation licence (Ror Ngor 4). The full schedule continues in steps up to 145,000 baht.

No machinery
1,000 baht
Under 50 horsepower
1,500 baht
50 to under 100 horsepower
3,000 baht
100 to under 200 horsepower
5,000 baht
200 to under 300 horsepower
7,000 baht
Top of the published schedule
145,000 baht

Who needs the licence, and where it is filed

The Factory Act sorts factories into categories, and the licence requirement under Section 12 attaches to the categories the Act reserves for prior approval. Whether a planned operation needs the full licence, a notification, or nothing at all is the first question a firm settles, because it decides the whole timeline.

A Bangkok factory files at the Department of Industrial Works service centre; a factory anywhere else files at the provincial industry office for the province where the site stands. The application form is the Ror Ngor 3, filed in two originals in Bangkok and three in the provinces. There is also an online route: the e-License system at the i-Industry portal, which requires registering on the portal first and lists a one month handling time.

How a factory licence application runs

  1. Confirm the category

    The factory list attached to the Act decides whether the operation needs a Section 12 licence at all. Getting this wrong in either direction is expensive.

  2. Prepare the site and process documentation

    The document list includes a production process chart identifying where wastewater, air emissions, industrial waste and other pollution arise, with the type, quantity and treatment method for each. This is the substantive review work.

  3. File the Ror Ngor 3

    Two originals in Bangkok at the Department of Industrial Works, three at a provincial industry office, or through the e-License system after registering on the i-Industry portal.

  4. Officials review29 to 30 days

    The published review time is 29 days for a complete paper application and 30 days through e-License. Unclear documents restart the clock through requests for clarification.

  5. Pay the fee and start up

    The licence fee follows the machine-power schedule. Test runs of machinery before full operation carry their own notification duty under the Act.

Firms

No firms listed yet

We do not have a verified firm specifically tagged for factory licensing services yet. You can still browse the wider Thailand directory.

Browse all firms

Note: BOI promotion changes the sequence, not the licence

A promoted project still needs its factory licence; the promotion certificate and the licence run as parallel workstreams with different agencies. Firms coordinating both usually sequence the BOI application first, because the promotion terms can change the machinery list the licence application describes. The background on what promotion actually grants is in our guide to BOI promotion in Thailand.

What the licence work actually involves

The legal work concentrates in three places. First, the category decision under the factory list, which decides the route. Second, the environmental file: the production chart with its pollution points and treatment methods is reviewed on substance, and weak treatment answers are the common reason applications stall. Where a project needs a formal environmental assessment, that runs through environmental law specialists before the licence file is complete. Third, the building and zoning fit: a factory needs a site where industrial use is lawful, and the licence review checks the location.

When to bring in a firm

A small operation renewing in place may need nobody. The cases that justify fees: a first licence for a new site, a foreign-owned operation structuring through a Thai company, category questions at the licence threshold, an environmental file that needs building from scratch, or a licence on a construction deadline. Factory licensing sits with corporate and business law firms in Thailand, and where the operating company is still being formed, the licence work runs alongside company registration in Thailand.

Common questions

Frequently asked questions

Where is a factory licence application filed?
In Bangkok, at the Department of Industrial Works service centre. Outside Bangkok, at the provincial industry office for the province where the factory stands. The e-License system on the i-Industry portal is the online route, and it requires registering on the portal before filing.
What documents does the application need?
The published list runs from the Ror Ngor 3 form and identity or company documents through to the technical file, including a production process chart that identifies where wastewater, air emissions, industrial waste and other pollution arise, with the type, quantity and treatment method for each.
How long does the review take?
The published figure is 29 days for a complete paper application and 30 days through e-License. Where officials find documents unclear or inaccurate, they request corrections, and the review continues on the corrected file.
Does a BOI-promoted project still need a factory licence?
Yes. Promotion and the factory licence come from different agencies and run in parallel. Firms usually sequence the promotion first, because its terms can change what the licence application describes.
Can a foreign-owned company hold a factory licence?
The licence itself attaches to the operator rather than a nationality, but the operating structure runs into the Foreign Business Act, land ownership limits for the site, and work permit requirements for foreign staff. A firm can set out the lawful structure before the licence work starts.